Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Get Your Money Refunded for Delay in Possession

Last Updated on June 15, 2024 by Satish Mishra

This time ‘ATS Green Golf Meadows’ has to face the music from Punjab State Consumer Dispute Redressal Commission for causing delay in possession of the unit to consumer who had approached the forum on account of deficiency in services.
See Also- CONSUMER COURT- A QUICK GUIDE FOR TRICITY

Facts
1 Applicant booked the plot in 2005. She paid 30 lacs as a cost of the plot

2 In April 2009, applicant was informed by builder that project is not approved and provisional allotment of plots could be made

3  Neither possession nor any progress was made on site.

4 In November 2012, builder asked applicant to pay EDC ( external development charges) plus 6.25 lacs was raised.

5 Builder alleged that applicant did not paid the EDC. Hence, she has filed the complaint in forum.

 

See Also- RERA or Consumer Forum?

Forums view
Punjab State Consumer Disputes Redressal Commission was not satisfied with the reply as the plots/flat was not delivered on time and asking EDC charges from customer was unjust and illegal.

Court Award

Punjab State Consumer Disputes Redressal Commission has asked ATS Infrastructure Limited Noida and ATS Estates Pvt Ltd Noida to refund 30 lacs to complainant with 12% interest, plus 21K as litigation expenses over and above 1lakh relief for delay in possession.

 

Also Read- Company refusing to pay health insurance? Remedy is with consumer court

Since the possession was not given on time the complainant has a right to withdraw from the scheme. It is clearly deficiency in services as held by the court.

See also- Builder Delaying Possession. What is your right?

 

Few Consumer Forum Decisions on Delay in Possession

1 Pay additional Rs. 2 lakh for delay in giving flat to homebuyer: MahaRERA asked developer in DNAIndia.com

2 MahaRERA issues first-ever recovery warrant against builder in DNAIndia.com

3 Unitech asked to refund over 1 crore to flat buyer for delay in handing over apartment in TheHindu

4 FIRM penalised for delay in possession of flat in TribuneIndia.com

5 Homebuyers should notice deficiencies before possession in TheHindu.com

6 Realty firm told to pay Rs 11 crore to 26 flat buyers in TimesOfIndia.com

 

Also Read- Legal Notice Before Consumer Complaint