Supreme Court Landmark Judgment on Compensation after Possession

In this post we will discuss about the most recent landmark judgment of The Hon’ble  Supreme Court in which it  held that  even after taking the possession of Flat/Unit/house and doing conveyance deed later, the homebuyer/complainants are entitled for delay interest or compensation.

It is a very rare chance that a consumer forum or state forum commission will entertain your complaint once you have taken the possession. There was no such precedent before; You can do the search yourself. There are many judgments on this sole ground only.

Then came the judgment of  Wg.Cdr Arifur Rahman Khan & Aleya Sultana & Othrs. Vs DLF Southern homes Pvt ltd decided on 24.08.2020 by Supreme Court of India in Civil Appeal no. 6239 of 2019 6303 of 2019. Here in this judgment Supreme Court held even after taking the possession of Flat/Unit/house and doing conveyance deed later, the homebuyer/complainants are entitled for delay interest or compensation interchangeably used.

Here’s what the court ordered:
1. Compensation @6% simple interest per annum from expiry of date of possession until the date of the offer of possession after the receipt of the occupation certificate.
2. This is in addition to Rs 5 per square foot given at the time of drawing final accounts.
3. The amount is to be paid within one month from the judgment.

The complaint was first files before NCDRC and then it came before The  Supreme Court in Appeal.
Supreme Court gave its findings on the following issues:
1. Compensation for delayed possession:

  • The fulcrum of the case of the developer rests on clause 14 of the ABA which is in the following terms:

“14. The Allottee agrees and understands that if the company is unable to give possession within the period as mentioned above or such extended period as permitted under this Agreement, due to reasons other than those mentioned in this Agreement, then the Company agrees to pay only to the Allottee and not to anyone else, subject to the Allottee, not being in default under any terms of this Agreement compensation @ Rs. 5/- per sq. feet of the Super Area of the said apartment per month for the period of such Delay. The adjustment of such compensation shall be done only at the time of execution of the Conveyance Deed of the Said Apartment    to the Allottee first named under this Agreement and not, earlier.”

  • Clause 11(a) of the ABA indicates that subject to “all just exceptions” the developer endeavoured to complete construction within a period of thirty-six months from the date of the execution of the agreement unless hindered by force majeure conditions. Undoubtedly, the expression ‘endeavour’ indicates that the developer did not bind itself to an inflexible timeline of thirty-six months. But then  again,  the  timeline of thirty-six moths was subject to just exceptions and could be excused in the event of force majeure conditions coming into operation. By the provisions of clause   14, the developer agreed to compensate the flat buyers at the rate of Rs. 5 per square feet of the super area of the apartment per month for the period of delay. According to the developer (i) the flat purchasers are bound by the above stipulations under which their entitlement was to receive compensation at the agreed rate (and hence not beyond); and (ii) no evidence has been adduced to indicate that the rate which has  been prescribed in the agreement is unreasonable. The developer relies on the observation in the decision of this Court in Dhanda11  that when parties have agreed to   a consequence of delay in handing over possession, there must be exceptional and strong reasons for the consumer fora to award compensation at more than the agreed rate. In assessing these submissions, we must at the outset note the submission of    Prashant Bhushan, learned Counsel that:

“There are a total of 4 blocks in ‘WESTEND HEIGHTS’ project. In Blocks A, B and  C, the delay is huge, over 4 years. For block D, the average delay is 2 years. Out of 339 complainants, for 268, the delay is huge, over 4 years.

The Builder sought repeated extension of time to deliver possession, vide communications dated 18.06.2013, 8.8.2013, 8.8.2014, 4.5.2015 etc.”

  • The extent of the delay as set out in the above submissions has not been controverted in the submissions which were urged before this Court by the developer. On the contrary, the finding of the NCDRC in paragraph 470 of its judgment is that:

“…there is no dispute to the fact that the completion of the project has been delayed. Delay has been acknowledged by the opposite parties….”

  • The existence and extent of the delay constitute an admitted factual position. In fact, in the written submissions which have been filed by the developer, it has been admitted that out of 171 appellants, 145 were given compensation in terms of the rate prescribed in clause 14 of the ABA. Once the developer has accepted that there was a delay on his part which triggered of the liability to pay compensation (albeit, according to the developer, in terms of clause 14) there can be no manner of doubt that:
  • the developer assumed an obligation in terms of the ABA to endeavour to hand over possession in thirty-six months of the date of the execution of the agreement;
  • there was a failure on the part of the developer to comply with the contractual obligation;
  • the failure of the developer was neither relatable to a “just exception” or the prevalence of force majeure conditions referable to clause 11; and
  • the payment of compensation to the flat buyers or at least 145 of the group of 171 represents an admission by the developer of its breach, thereby triggering a liability to pay
  • The only issue which then falls for determination is whether the flat buyers in these circumstances are constrained by the stipulation contained in clause 14 of ABA providing compensation for delay at the rate of Rs. 5 per square feet per month. In assessing the legal position, it is necessary to record that the ABA is clearly one-sided. Where a flat purchaser pays the instalments that are due in terms of the agreement with a delay, clause 39(a) stipulates that the developer would “at its sole option and discretion” waive a breach by the allottee of failing to make payments in accordance with the schedule, subject to the condition that the allottee would be charged interest at the rate of 15 per cent per month for the first ninety days and thereafter at an additional penal interest of 3 per cent per annum. In other words, a delay on the part   of the flat buyer attracts interest at the rate of 18 per cent per annum beyond ninety days. On the other hand, where a developer delays in handing over possession the flat buyer is restricted to receiving interest at Rs. 5 per square foot per month under    clause 14 (which in the submission of Mr. Prashant Bhushan works out to 1-1.5 per   cent interest per annum). Would the condition which has been prescribed in clause 14 continue to bind the flat purchaser indefinitely irrespective of the length of the delay? The agreement stipulates thirty-six months as the date for the handing over of possession. Evidently, the terms of the agreement have been drafted by the  They do not maintain a level platform as between the developer and purchaser. The stringency of the terms which bind the purchaser are not mirrored by the obligations for meeting times lines by the developer. The agreement does not   reflect an even bargain.
  • On behalf of the flat purchasers it has been urged by Mr. R Balasubramanian (a submission which has not been controverted in rejoinder) that 95 per cent of the purchase price was paid during the course of the first two and a half to three years. The agreement did not stipulate that the developer would pay any interest on the amount which had already been received. A large chunk of the purchase price was    thus available to the developer to complete construction. The court must take a robust and common-sense based approach by taking judicial notice of the fact that flat purchasers obtain loans and are required to pay EMIs to financial institutions for servicing their debt. Delays on the part of the developer in handing over possession postpone the date on which purchasers will obtain a home. Besides servicing their   loans, purchasers have to finance the expenses of living elsewhere. To postulate that a clause in the agreement confining the right of the purchaser to receive compensation    at the rate of Rs. 5 per square foot per month (Rs. 7,500 per month for a flat of 1500 square feet) precludes any other claim would be a  manifestly  unreasonable construction of the rights and obligations of the parties. Where there is a delay of the nature that has taken place in the present case ranging between periods of two years and four years, the jurisdiction of the consumer forum to award reasonable compensation cannot be foreclosed by a term of the agreement. The expression deficiency of services is defined in Section 2(1)(g) of the CP Act 1986 as:

“(g) “deficiency” means any fault, imperfection, shortcoming or inadequacy in    the quality, nature and manner of performance which is required to be maintained   by or under any law for the time being in force or has been undertaken to be performed by a person in pursuance of a contract or otherwise in relation to any service”

  • A failure of the developer to comply with the contractual obligation to provide

the flat to a flat purchaser within a contractually stipulated period amounts to a deficiency. There is a fault, shortcoming or inadequacy in the nature and manner of performance which has been undertaken to be performed in pursuance of the contract  in relation to the service. The expression ‘service’ in Section 2(1)(o) means a service    of any description which is made available to potential users including the provision of facilities in connection with (among other things) housing construction. Under Section 14(1)(e), the jurisdiction of the consumer forum extends to directing the opposite    party inter alia to remove the deficiency in the service in question. Intrinsic to the jurisdiction which has been conferred to direct the removal of a deficiency in service is the provision of compensation as a measure of restitution to a flat buyer for the delay which has been occasioned by the developer beyond the period  within  which  possession was to be handed over to the purchaser. Flat purchasers suffer agony and harassment, as a result of the default of the developer. Flat purchasers  make  legitimate assessments in regard to the future course of their lives based on the flat which has been purchased being available for use and occupation. These legitimate expectations are belied when the developer as in the present case is guilty of a delay    of years in the fulfilment of a contractual obligation. To uphold the contention of the developer that the flat buyer is constrained by the terms of the  agreed  rate  irrespective of the nature or extent of delay would result in a miscarriage of justice. Undoubtedly, as this court held in  Dhanda, courts ordinarily would hold parties down   to a contractual bargain. Equally the court cannot be oblivious to the one-sided nature  of ABAs which are drafted by and to protect the interest of the developer. Parliament consciously designed remedies in the CP Act 1986 to protect consumers. Where, as in the present case, there has been a gross delay in the handing over of possession  beyond the contractually stipulated debt, we are clearly of the view  that  the  jurisdiction of the consumer forum to award just and reasonable compensation as an incident of its power to direct the removal of a deficiency in service is not constrained   by the terms of a rate which is prescribed in an unfair bargain.

  • Numerous judgments of this Court have elaborated on the nature and extent of the jurisdiction of the consumer forum to award just and reasonable compensation. Since the decision of this Court in Lucknow Development Authority v. M K Gupta16, it has been a settled principle of law that the jurisdiction of the consumer forum extends  to the award of compensation to alleviate the harassment and agony to a consumer. In Balbir Singh17, a two judge Bench of this Court, while explaining the ambit of the jurisdiction of the adjudicatory fora under the CP Act 1986 observed:

“6…The word compensation is of a very wide connotation.  It  may  constitute actual loss or expected loss and may extend to compensation for physical, mental    or even emotional suffering, insult or injury or loss. The provisions of the Consumer Protection Act enable a consumer to claim and empower the Commission to redress any injustice done.”

  • The court observed that the award of compensation has to be based on a finding of loss or injury and must correlate to it. The court observed that no “hard and fast rule” could be prescribed:

“8…No hard-and-fast rule can be laid down, however, a few examples would be where an allotment is made, price is received/paid but possession is not given    within the period set out in the brochure. The Commission/Forum would then need   to determine the loss. Loss could be determined on basis of loss of rent which could have been earned if possession was given and the premises let out or if the  consumer has had to stay in rented premises then on basis of rent actually paid by him. Along with recompensing the loss the Commission/Forum  may  also  compensate for harassment/injury, both mental and physical.”

  • Where possession has been given, one of the circumstances which must be

factored in is that the purchaser has been compensated by the increase in the value of the property.

  • In R V Prasannakumaar v. Mantri Castles Pvt. Ltd.18under the terms of the

ABA, possession of the flats was to be handed over to the buyers on 31 January 2014. However, the developer received an occupation certificate only on 10 February 2016  and it was thereafter from May 2016 that the developer started issuing letters offering possession. Based on this, the NCDRC awarded compensation in the form of interest at the rate of 6 per cent per annum. The developer had pleaded that since the agreement provided compensation at the rate of Rs. 3 per square foot per month for delayed possession, the purchasers were not entitled to anything in addition. Dealing with the submission, this Court observed:

“9. We are in agreement with the view of the NCDRC that the rate which has   been stipulated by the developer, of compensation at the rate of 3 per sq. ft. per month does not provide just or reasonable recompense to a flat buyer who has invested money and has not been handed over possession as on the stipulated date  of 31 January 2014. To take a simple illustration, a flat buyer with an agreement of   a flat admeasuring a 1000 sq. ft. would receive, under the agreement, not more   than Rs. 3000/- per month. This in a city such as Bangalore does not provide just or adequate compensation. The jurisdiction of the NCDRC to award just compensation under the provisions of the Consumer Protection Act, 1986 cannot in the circumstances be constrained by the terms of the agreement. The agreement in its view is one sided and does not provide sufficient recompense to  the  flat  purchasers.”

  • The Court observed that there was a delay of two years and hence the award of interest at the rate of 6 per cent was reasonable and
  • In Pioneer Urban Land and Infrastructure Limited v. Govindan  Raghavan19, there was a delay of almost two years in obtaining an occupancy certificate after the date stipulated in the ABA. As a consequence, there was a failure  to  provide  possession of the flat to the purchaser within a reasonable period. This Court dwelt on the terms of the ABA under which the builder was entitled to charge interest at 18 per cent per annum for the delay in payment of instalments by the purchaser. On the    other hand, the failure to provide possession on the part of the developer was subject   to a grace period of twelve months followed by a termination notice of ninety days and   a further period of ninety days to the developer to effect a refund. Adverting to these clauses, the court noted:

“6.4. A perusal of the apartment buyer’s agreement  dated  8-5-2012  reveals stark incongruities between the remedies available to both the parties. For instance, Clause 6.4(ii) of the agreement entitles the appellant builder to charge interest  @18% p.a. on account of any delay in payment of instalments from the respondent flat purchaser. Clause 6.4(iii) of the agreement entitles the appellant builder to  cancel the allotment and terminate the agreement, if any instalment remains in arrears for more than 30 days. On the other hand, as per Clause 11.5 of the agreement, if the appellant builder fails to deliver possession of  the  apartment within the stipulated period, the respondent flat purchaser has to wait for a period    of 12 months after the end of the grace period, before serving a termination notice   of 90 days on the appellant builder, and even thereafter, the appellant builder gets  90 days to refund only the actual instalment paid by the respondent flat purchaser, after adjusting the taxes paid, interest and penalty on delayed payments. In case of any delay thereafter, the appellant builder is liable to pay interest @9% p.a. only.

6.5. Another instance is Clause 23.4 of the agreement which entitles  the  appellant builder to serve a termination notice upon the respondent flat purchaser   for breach of any contractual obligation. If the respondent flat purchaser fails to rectify the default within 30 days of the termination notice, then the agreement automatically stands cancelled, and the appellant builder has the right to forfeit the entire amount of earnest money towards liquidated damages. On the other hand, as per Clause 11.5(v.) of the agreement, if the respondent flat purchaser fails  to exercise his right of termination within the time limit provided in Clause 11.5, then  he shall not be entitled to terminate the agreement thereafter, and shall be bound   by the provisions of the agreement.”

  • Justice Indu Malhotra speaking for the Court noted:

“6.8. A term of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by    the builder. The contractual terms of the agreement dated 8-5-2012 are ex facie one-sided, unfair and unreasonable. The incorporation of such one-sided clauses in an agreement constitutes an unfair trade practice as per Section 2(1)(r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by the builder.”

  • The Court observed that in these circumstances, the flat purchasers could not be compelled to obtain possession which was offered almost two years after the grace period under the agreement had expired. Hence, the NCDRC was held  to  have correctly awarded interest at the rate of 10 percent per
  • The decision of this Court in Dhanda20has been relied upon by learned Senior Counsel appearing on behalf of the developer as elucidating the principle that where a flat buyers’ agreement stipulates a consequence for delayed possession, exceptional  and strong reasons must be established before the forum constituted under the Act of 1986 awards compensation in addition to what has been contractually agreed. In Dhanda’s  case, the SCDRC issued a direction for handing over physical possession of  the residential unit to the complainant and for execution of a sale deed. In addition, compensation was awarded by way of interest at the rate of 12 per cent per annum   with effect from twelve months after the stipulated date under the agreement. In an appeal by the developer, the NCDRC directed that the rate of interest for a house building loan for the corresponding period in a scheduled nationalised bank would be appropriate and if a floating rate of interest was prescribed, the higher rate of interest should be taken for the computation. A sum of Rs. 1 lac per annum from the date for handing over possession to the actual date of possession was regarded as appropriate   in the facts of the case. In that case under the terms of the buyer’s agreements, possession was to be delivered within twenty-four months of the execution of the agreement i.e. 10 February 2013 – failing which the developer was liable to pay compensation at the rate of Rs. 10 per square foot per month for the delay. The developer contended that construction activities were delayed as a result of an  injunction granted by this Court over a period of eight  months  and  consequently sought an extension of the period for handing over possession by one year. Alternatively, the developer offered to refund the money deposited with interest at 9   per cent per annum. Construction of 258 independent floors  was  completed  while about 1,500 units were nearing completion. In two sets of Civil Appeals which came     up before this Court earlier, agreed terms were arrived at providing for the award of interest at 9 per cent per annum from the date of deposit till refund. While considering the order of the NCDRC, this Court observed:

“16. The District Forum under the Consumer Protection Act, 1986 is empowered inter-alia to order the opposite party to pay such amount as may be awarded as compensation to the consumer for any loss or injury suffered by the consumer due   to the negligence of the opposite party including to grant punitive damages. But     the forums under the Act cannot award interest and/or compensation by applying  rule of thumb. The order to grant interest at the maximum of rate of interest charged by nationalised bank for advancing home loan is arbitrary and no nexus   with the default committed. The appellant has agreed to deliver constructed flats.   For delay in handing over possession, the consumer is entitled to the consequences agreed at the time of executing buyer’s agreement. There cannot be multiple heads  to grant of damages and interest when the parties have agreed for payment of damages at the rate of Rs. 10/- per sq. ft. per month. Once the parties agreed for a particular consequence of delay in handing over of possession then, there has to be exceptional and strong reasons for the SCDRC/NCDRC to award compensation at more than the agreed rate.”

  • The orders of the SCDRC and NCDRC were held to be without any foundation being led by the complainant and based purely on a “rule of thumb”. The court noted that the amount of interest represents compensation to the beneficiaries who are deprived of the use of the investment which has been made and will take into its ambit the consequence of a delay in not handing over possession. The court held that both the SCDRC and NCDRC awarded compensation under different heads on account   of a singular default of not handing over possession. This was held not to be The court held that:

“19. Thus, we find that the complainant is entitled to interest from the Appellant for not handing over possession as projected as is offered by it but it is not a case    to award special punitive damages as one of the causes for late delivery of  possession was beyond the control of the Appellant. Therefore, in view of the settlement proposal submitted by the Appellant in earlier two set of appeals in  respect of same project, and to settle any further controversy, the Appellant is directed as follows:

  1. To send a copy of the occupation certificate to the Complainants along with offer of possession. The Appellant shall also direct the Jones Lang LaSalle – the real estate maintenance agency, engaged by the Appellant to undertake such maintenance works as is necessary on account of damage due to non- occupation of the flats after construction
  2. It shall be open to the Complainants to seek the assistance of  the  maintenance agency to attend to the maintenance work which may arise on account of non-occupation or on account of natural
  • Such maintenance work shall be completed by the Appellant within two months of the offer of possession but the payment of interest at the rate of 9 per cent per annum will be for a period of two months from the date of offer of possession in all
  1. Since the Complainants have been forced to invoke jurisdiction of the  consumer forums, they shall be entitled to consolidated amount of    50,000/- in each complaint on all accounts such as mental  agony  and  litigation expenses etc. The complainant shall not be entitled to any other amount over and above the amount mentioned above.
  2. In case, the original allottee has transferred the flat, the transferee shall be entitled to interest at the rate of 9 per cent per annum from the date of expiry of three years from the agreement or from the date of transfer, whichever is later.”

ALSO READ- GET YOUR MONEY REFUNDED FOR DELAY IN POSSESSION

  • The judgment in Dhanda’s case does not prescribe an absolute embargo on the award of compensation beyond the rate stipulated in the flat buyers’ agreement where handing over of the possession of a flat has been delayed. Dhanda’s case  was  preceded by consent terms which were presented before this Court in two earlier civil appeals under which interest at the rate of 9 per cent had been granted. The decision lays down that the award of interest cannot be arbitrary and without nexus to the  default which has been Hence, the award of interest at the maximum rate of interest charged by a nationalised bank for advancing home loans was construed to be arbitrary. It was in this context that the court observed that the parties having agreed to a consequence for delay, exceptional and strong reasons must exist for the consumer fora to depart from the agreed rate. The decision, in other words, does not  lay down that there is an absence of jurisdiction in the adjudicatory fora constituted under the CP Act 1986 to award remedial compensation to a flat buyer for the delay of the developer in handing over possession on the agreed date.
  • In the present case, there exist, clear and valid reasons for not holding down the flat buying consumers merely to the entitlement to receive compensation at the   rate of 5 per square foot per month in terms of clause 14 of the ABA:
  • There has been a breach on the part of the developer in complying with the contractual obligation to hand over possession of the flats within a period of thirty-six months of the date of the agreement as stipulated in clause 11(a);
  • The failure of the developer to hand over possession within the contractually stipulated period amounts to a deficiency of service within the meaning of  Section 2(1)(g), warranting the invocation of the jurisdiction vested  in  the  NCDRC to issue a direction for the removal of the deficiency in service;
  • The triggering of an obligation to pay compensation on the existence of delay in handing over possession is admitted by the developer for, even according to it, it has adjusted compensation at the agreed rate of Rs. 5 per square foot per month to 145 out of the 171 appellants;
  • The agreement is manifestly one-sided : the rights provided to the developer for a default on the part of the home buyer are not placed on an equal platform with the contractual right provided to the home buyer in the case of a default by the developer;
  • There has been a gross delay on the part of the developer in completing construction ranging between two and four years. Despite successive extensions of time to deliver possession sought by the developer, possession was not delivered on time;
  • The nature and quantum of the delay on the part of the developer are of such a nature that the measure of compensation which is provided in clause 14 of the ABA would not provide sufficient recompense to the purchasers; and
  • Judicial notice ought to be taken of the fact that a flat purchaser who is left in the lurch as a result of the failure of the developer to provide possession within the contractually stipulated date suffers consequences in terms of agony and hardship, not the least of which is financial in nature. Having paid a substantial amount of the purchase price to the developer and being required to service the debt towards loan installments the purchaser is unable to obtain  timely  possession of the flat which is the subject matter of the

But, it has been submitted by the developer – a submission which found acceptance by the NCDRC – that the execution of the Deed of Conveyance by a flat purchaser precludes a consumer claim being raised for delayed possession. During the course of the proceedings before the NCDRC, the flat purchasers relied upon the communications which were issued by the developer to demonstrate that the  purchasers were not permitted by the developer to execute a Deed of Conveyance or    to take possession under protest. The material which was produced before the NCDRC supports this submission, which was urged before the Court by Mr. Prashant Bhushan, learned Counsel. By a communication dated 16 February 2016, the developer informed  a flat buyer that in terms of the ABA, the allottee is required to take possession of the apartment by making payments and executing documentation after the developer has obtained a certificate for occupation from the competent authority and has offered possession of the apartment to the allottee. The developer stated: “We may also like to bring to your notice, that if the acceptance of offer of possession terms is being conveyed by the allottee under protest the Company will not be in a position to hand over the possession and execute the Conveyance Deed and as such your request to take over the possession and execute the documents under protest is untenable.”

  • By an email dated 24 December 2016, another flat buyer was informed that:

“It would be a pleasure to progress with possession once you  submit  the  affidavit. However we can’t accept any documents to this effect under protest or  claim of coercion. This affidavit has to be unconditionally submitted and possession taken.”

  • By another communication dated 21 December 2016, a flat purchaser was informed that:

“It was explained to you in our FDN itself and our earlier reply/clarifications, that any kind of protest ‘is not tenable if you wish to take possession and register the property as well. Kindly execute the affidavit as advised and proceed for further process on registering the property.”

  • By a communication dated 1 December 2016, the developer informed a flat purchaser that

“Your letter that you took possession and executed the documents under protest   is untenable and unacceptable and the company will not be in a position to execute the conveyance deed under protest.”

  • Copies of these communications are marked as Annexures P-28, P-29, P-30 and P-31 to Civil Appeal 6239 of
  • The developer has not disputed these communications. Though these are four communications issued by the developer, the appellants submitted that they are not isolated aberrations but fit into a pattern. The developer does not state that it was willing to offer the flat purchasers possession of their flats and the right to execute conveyance of the flats while reserving their claim for compensation for delay. On the contrary, the tenor of the communications indicates that while executing the Deeds of Conveyance, the flat buyers were informed that no form of protest or reservation would be acceptable. The flat buyers were essentially presented with an unfair choice    of either retaining their right to pursue their claims (in which event they would not get possession or title in the meantime) or to forsake the claims in order to perfect their  title to the flats for which they had paid valuable consideration. In this backdrop, the simple question which we need to address is whether a flat buyer  who  seeks  to espouse a claim against the developer for delayed possession can as a consequence of doing so be compelled to defer the right to obtain a conveyance to perfect their title. It would, in our view, be manifestly unreasonable to expect that in order to pursue a   claim for compensation for delayed handing over of possession, the purchaser must indefinitely defer obtaining a conveyance of the premises purchased or, if they seek to obtain a Deed of Conveyance to forsake the right to claim compensation. This basically  is a position which the NCDRC has We cannot countenance that view.
  • The flat purchasers invested hard earned money. It is only reasonable to presume that the next logical step is for the purchaser to perfect the title to the premises which have been allotted under the terms of the ABA. But the submission of the developer is that the purchaser forsakes the remedy before the consumer forum by seeking a Deed of Conveyance. To accept such a construction would lead to an absurd consequence of requiring the purchaser either to abandon a just claim as a condition for obtaining the conveyance or to indefinitely delay the execution of the Deed of Conveyance pending protracted consumer

It has been urged by the learned counsel of the developer that a consequence   of the execution of the Deed of Conveyance in the present case is that the same ceases to be a transaction in the nature of “supply of services” covered under the CP   Act 1986 and becomes a mere sale of immovable property which is not amenable to   the jurisdiction of Consumer Fora. In Narne Construction (P) Ltd. v. Union of India21,  this Court distinguished between a simple transfer of a piece of immovable property   and housing construction or building activity carried out by a private or statutory body falling in the category of ‘service’ within the meaning of Section 2(1)(o) of the CP Act 1986. This Court held that:

“8. Having regard to the nature of transaction between the appellant Company  and its customers involved much more than a simple transfer of a piece of  immovable property it is clear the same constitutes “service” within the meaning of the Act. It was not the case that the appellant Company was selling the given property with all its advantages and/or disadvantages on “as is where is” basis, as was the position in UT Chandigarh Admn v. Amarjeet Singh. It is a case where a clear-cut assurance was made to the purchasers as to the nature and extent of development that would be carried out by the appellant Company as a part of package under which a sale of fully developed plots  with  assured  facilities  was made in favour of the purchasers for valuable consideration. To the extent the transfer of site with developments in the manner and to the extent indicated earlier was a part of the transaction, the appellant Company has indeed undertaken to provide a service. Any deficiency or defect in such service would  make  it  accountable before the competent Consumer Forum at the instance of consumers   like the respondents.”

  • The developer in the present case has undertaken to provide a service in the nature of developing residential flats with certain amenities and remains amenable to the jurisdiction of the Consumer Fora. Consequently, we are unable to subscribe to the view of the NCDRC that flat purchasers who obtained possession or executed Deeds of Conveyance have lost their right to make a claim for compensation for the delayed handing over of the
  • However, the cases of the eleven purchasers who entered into specific settlement deeds with the developers have to be segregated. In the case of these eleven persons, we are of the view that it would be appropriate if their cases are excluded from the purview of the present order. These eleven flat purchasers having entered into specific deeds of settlement, it would be only appropriate and proper if   they are held down to the terms of the bargain. We are not inclined to accept the contention of the learned counsel of the appellants, Mr. Prashant Bhushan, that the settlement deeds were executed under coercion or undue influence since no specific material has been produced on record to demonstrate the
  • Similarly, the three appellants who have transferred their title, right and  interest in the apartments would not be entitled to the benefit of the present order   since they have sold their interest in the apartments to third parties. The written submissions which have been filed before this Court indicate that “the two buyers stepped into the shoes of the first buyers” as a result of the assignment of rights and liabilities by the first buyer in favour of the second buyer. In HUDA v. Raje Ram22, this Court while holding that a claim of compensation for delayed  possession  by  subsequent transferees is unsustainable, observed that:

“7. Respondents in the three appeals are not the original allottees. They are re- allottees to whom re-allotment was made by the appellant in the years 1994, 1997 and 1996 respectively. They were aware, when the plots were re-allotted to them, that there was delay (either in forming the layout itself or delay in delivering the allotted plot on account of encroachment etc). In spite of it, they took re-allotment. Their cases cannot be compared to cases of original allottees who were made to    wait for a decade or more for delivery and thus put to mental agony and harassment. They were aware that time for performance was not stipulated as the essence of the contract and the original allottees had accepted the delay.” Even if the three appellants who had transferred their interest in  the  apartments had continued to agitate on the issue of delay of possession, we are not inclined to accept the submission that the subsequent transferees can step into the shoes of the original buyer for the purpose of benefiting from this order. The  subsequent transferees in spite of being aware of the delay in delivery of possession   the flats, had purchased the interest in the apartments from the original  buyers. Further, it cannot be said that the subsequent transferees suffered any agony and harassment comparable to that of the first buyers, as a result of the delay in the  delivery of possession in order to be entitled to compensation.

ALSO READ- HOW TO TRANSFER CASE TO RERA FROM CONSUMER FORUM

2.Amenities

  • The brochure that was issued by the developers spoke of a “Distinctive DLF Living” while advertising the project, which was described as “DLF Westend Heights”, New Town. This was described as “the premier choice for Bangalore living…a premium residential enclave featuring spacious apartments with a rich selection of amenities.” Westend Heights at New Town was described as a project which was being developed on a land area of 27.5 acres. The brochure specifically referred to the amenities being provided. Among them were (i) “The most exclusive club in Bangalore”; (ii)  a  swimming pool; (iii) gymnasium/aerobics centre; and (iv) a restaurant and  Bar  together with other sports facilities. Besides this, the brochure contained a representation of the setting up of a convenience shopping centre with an array of outlets, a renowned early – learning school and state of the art health care facilities. Clause 1.10(a) of the ABA, which imposes the liability to bear taxes on the allottees states that this liability will be proportionate to the ratio of the super area of the apartment to the total super area of all the apartments and other “shops, clubs etc” in the said
  • The grievance in regard to the alleged failure of the developer to provide amenities may be divided into two segments:
  • The club house; and
  • Other amenities

  1. Clubhouse
  • The developer has stated before the court that a club house containing appurtenant facilities including a swimming pool, gymnasium, billiards room, tennis court, indoor badminton court, squash court and community hall has been fully constructed and an occupation certificate has been received on 13 May 2019. The developer has stated that under the building regulations, it has to handover 5 per cent of the area of the group housing complex to BDA as a civic amenities (“CA”) area. The RWA has to apply to BDA for allotment of the CA area in its favour. Upon allotment,    the RWA hands over the area to the builder for construction of the club. The developer relinquished the CA area in favour of the BDA, constituted an RWA and applied to BDA on 22 June 2010 for the allotment of the CA site in favour of the RWA. The written submissions indicate that a dispute over the charges demanded by BDA towards lease rent led to a writ petition before the Karnataka High Court being instituted both by the developer and the RWA which was allowed on 29 June 2015. The developer submitted   a building plan to the municipal body. A second writ petition had to be filed in which    the High Court on 18 October 2016 directed the municipal body to proceed with the approval of the building plans. Sanction for the building plan was received on 18 May 2017 and after construction of the club building, an occupation certificate was received on 13 May 2019. The developer has stated that it has been following up with BDA to permit them to hand over possession and management of the club to the RWA. Since permission of BDA has still not been received legal action is contemplated The

developer has produced photographs depicting the amenities which  have  been  provided within the precincts of the club house. Membership fees for the club are    stated to have been received in the account of the RWA and not in the account of the developer. The position which has been stated before the court as elucidated above    has not been disputed by counsel for the appellants. Hence, we find that there has   been no breach by the developer of the obligation to provide a constructed facility of a club for the RWA.

ALSO READ- HOW TO FILE RERA COMPLAINT ONLINE WITH RERA PANCHKULA AUTHORITY

  1. Other amenities
  • As regards the other amenities, the defence of the developer is that these were to be developed as an integral element of the entire township of 80 acres of which the project admeasuring 27 acres (comprised in Westend Heights) was a part. The ABA stipulates that allottees of the complex have no right, title and interest in respect of the amenities or facilities outside the residential complex, which lie within the larger township. According to the developer, no part of the consideration which was paid by allottees, including the appellants, was towards the amenities and facilities falling outside the boundary of the complex. In this regard, the developer relies on the following stipulation accepted by allottees under clause 5 of the Booking Application Form:

“The applicant confirms and represents that he has not made any payment to the Company in any manner whatsoever and that the Company has not indicated/premised/represented/given any impression of any kind in an explicit or implicit manner whatsoever, that the Applicant shall have any right, title or interest of any in whatsoever in any lands, buildings, common areas, facilities and amenities failing outside the Said Complex…”

  • The above stipulation is reiterated under clause 1.21 of the ABA:

“The allottee acknowledges and confirms that the allottee is not entitled to or has not paid for the lands outside the said land/said complex whether the same is     within said project or other. The said project would comprise of many complexes similar on different to said complex. Allottee has not paid any amount towards any other lands, areas, facilities and amenities including but not limited to those listed below, and as such, the allottee shall have no right interest of any  nature  whatsoever in the same and the same are specifically excluded from the scope of   this agreement. The allottee acknowledges that the ownership of such land and facilities and amenities shall vest solely with the company/LDC and its associate companies subsidiaries and they alone shall have sole right and absolute authority    to deal with the same including their usage and manner/method of use, disposal    etc. creation of rights in favour of other person by way of sale, transfer, lease Joint venture, collaboration or any other including transfer of government, semi- government, any other person.”

  • Now, it is correct as the developer contends that the flat purchasers have no right, title or interest in respect of the amenities which were to be constructed by the developer as a part of the larger township of New Town. The entire area comprised 80 acres of which Westend Heights was situated on 27 acres. The absence of a title or interest in the flat purchasers in the amenities to be provided outside the area of 27 acres begs the question as to whether there was a breach of a clear representation which was held out to the flat purchasers by the developer. A deficiency under Section 2(1)(g) means a fault, imperfection, shortcoming or inadequacy in the quality, nature and manner of performance. This may be required to be maintained under law or may be undertaken to be performed in pursuance of a contract or otherwise in relation to  any service. The builder invited prospective flat purchasers to invest in the project of Westend Heights on the basis of a clear representation that the surrounding area of  New Town situated on 80 acres was being developed to provide a wide range of

amenities including a shopping centre, health care facilities and an  early  learning school. The developer has failed to provide these amenities. In the  reply,  the  developer has stated that:

“It is stated that School, Commercial Complex and Health clinic are part of the facility which will be provided upon the completion of the Whole New Town project   as these facilities, with existing population cannot sustain these facilities. Every matter has to be adjudicated in light of its own facts and circumstance…”

  • In the written submissions of the developer, the failure to provide the amenities is sought to be glossed over by contending that:

“…the issue of these facilities has since become completely academic since the  area around the DLF Township has already become totally urbanized and well developed thanks in larger measure due to the DLF’s activities in the area and there are now many proximate hospitals, schools, shopping areas that have mushroomed  in the immediate vicinity and neighbourhood of the DLF Township which are in fact being regularly and conveniently used by the residents of the DLF  residential  complex which include the Appellants herein. As such, there is no loss or claim for  any damages that could be said to have accrued to the Appellants either under the ABA or otherwise under this alleged head of claim.”

  • In other words, what the developer holds out as a defence is that though there has been a failure on their part to provide the amenities, the flat buyers have the benefit of facilities in the surrounding area which has become urbanised. We cannot agree with this line of submissions. The reply of the developer seeks to explain the failure to construct the facilities on the ground that the “existing population cannot sustain these facilities” – a school, commercial complex and health care facilities. This is a case involving an experienced developer who knew the nature of  the  representation which was being held out to the flat purchasers. Developers sell dreams to home buyers. Implicit in their representations is that the facilities which will be developed by the developer will provide convenience of living and a certain lifestyle based on the existence of those amenities. Having sold the flats, the developer may   find it economically unviable to provide the amenities. The flat purchasers cannot be   left in the lurch or, as in the present case, be told that the absence of facilities which were to be provided by the developer is compensated by other amenities which are available in the area. The developer must be held accountable to its representation. A flat purchaser who invests in a flat does so on an assessment of its potential. The amenities which the builder has committed to provide impinge on the quality of life for the families of purchasers and the potential for appreciation in the value of the flat.    The representation held out by the developer cannot be dismissed as chaff. True, in a situation such as the present it may be difficult for the court to quantify the exact  nature of the compensation that should be provided to the flat buyers. The general appreciation in land values results in an increase in the value of the investment made  by the buyers. Difficulties in determining the measure of  compensation  cannot  however dilute the liability to pay. A developer who has breached  a  clear  representation which has been made to the buyers of the amenities which will be provided to them should be held accountable to the process of law. To allow the developer to escape their obligation would put a premium on false assurances and representations made to the flat purchasers. Hence, in factoring in the compensation which should be provided to the flat buyers who are concerned in the present batch of appeals, we would necessarily have to bear this issue in

5.Tax

  • The ABA contained specific provisions in regard to the payment of Clause

1.3 of the ABA provided:

“1.3 The Allottee shall make the payment of the Total price as per the payment

plan set out in annexure-III of this Agreement. Other charges, securities, payments etc. (as specified in this Agreement), Taxes and increase thereof (as provided in clause 1.10) shall be payable by the Allottee, as and when demanded by the Company.”

  • Clause 1.10 contained a specific provision in regard to the obligation of the allottee to pay taxes in addition to the total price. Clause 1.10 provided:

“1.10. The Allottee agrees and understands that in addition to Total price, the Allottee shall be liable to pay the Taxes, which shall be charged and paid as under:

  1. A sum equivalent to the proportionate share of Taxes shall be paid by the Allottee to the Company. The Proportionate share shall be the ratio of the Super Area of the said Apartment to the total super area of all the apartments other buildings shop, club etc. in the said
  2. The Company shall periodically intimate to the Allottee herein, on the basis of certificates from a Chartered Engineer and/or a Chartered• Accountant, the amount payable as stated above which shall be final and binding on  the Allottee and the Allottee shall make payment of such amount within 30 (thirty days) of such ”
  • The ABA also contains the following provisions:

“2. Payment for taxes on land, wealth-tax, cesses etc. by Allottee:—

The Allottee agrees and confirms to pay all Government rates, tax on land, municipal tax, property taxes, wealth tax, Building and Other Construction  Workers Welfare Fund (Cess), taxes, one time building tax, luxury tax if any, fees or levies of all and any kind by whatever name called, whether levied or Leviable now or in future by the Government or municipal authority or any other governmental authority on the Said Complex and I or the Said Building or land appurtenant thereto as the case may be as assessable or applicable from the    date of the Application if the Said Apartment is assessed separately and if the   Said Apartment is not assessed separately then the Allottee shall pay directly to the concerned authority and if the same is levied on or paid by the Company or  the Allottee then the same shall be borne and paid by the Allottee on pro-rata  basis and such determination of proportionate share by the Company  and  demand shall be final and binding on the Allottee. However, if  the  Said  Apartment is assessed separately the Allottee shall pay directly to  the  Government Authority.

3. Amount paid by Allottee with Application

The Allottee has paid a sum of Rs. 3,00,000/- (Rupees 3  Lakhs  only)  alongwith the Application, the receipt of which the Company doth hereby acknowledge and the Allottee agrees to pay the remaining price of the Said Apartment as prescribed in schedule of payments (Annexure-III) attached with  this Agreement along with all other charges, Taxes, securities etc. as mentioned   in this Agreement and as per the de-mand raised by the Company in accordance with the Agreement.”

  • The ABA contains the definition of taxes in the following terms:

““Taxes” shall mean any and all taxes payable by the Company/LOC and/or its contractors, suppliers, consultants, etc. by way of value added tax (VAT), state    sales tax, central sales tax, works contract tax, service tax, cess, levies and educational cess and any other taxes levies, charges by  whatever  name  called levied and collected by Government Agency in connection with Development/construction of the Said Apartment/Said Building/Said Complex.”

  • The expression total price is also defined in the ABA so as to be exclusive inter alia of The two certificates of the Chartered Accountant issued on 26 July 2013 and 9 August 2014 indicate that taxes inclusive of interest have been recovered. According to the appellants, the builder admitted that it had “not  properly  discharged”  his  liability towards taxes for a period of thirty-six months between 2011-2012 and 2013- 2014 and that tax dues were paid on 25 March 2015 together with  penalty  and interest. Hence, it has been urged that the liability to pay interest which arose on account of the default of the developer in discharging the tax liability on time cannot    be fastened upon the buyers.
  • On behalf of the developer it has been submitted that when construction commenced in 2009, there was an absence of clarity on whether works contract tax was liable to be paid in relation to agreements between owners-developers  and  allottees of apartments where the apartments were to be delivered in future. In 2013, this Court delivered its judgment in Larsen and Toubro Limited v. State of Karnataka23   as a result of which the liability towards works contract tax was adjudicated upon. Consequently, while computing the amount payable in the final statements of accounts, the developer passed on the interest burden but not the penalty on a proportionate basis in terms of clause 1.10. The allottees were required to pay their proportionate share of the works contract tax in terms of the ABA and the final demand was raised at the time of the offer of
  • The specific conditions contained in the ABA clearly imposed the liability to bear the proportionate share of taxes on the purchasers. Clauses 1.3 and 1.10 leave no manner of doubt in regard to the position. The developer has offered an explanation of why as a result of pending litigation, the dues towards works contract tax were not  paid earlier. Indeed, if they were paid earlier, the purchasers would have been required to reimburse their proportionate share of taxes earlier as well. No part of the penalty imposed on the developer has been passed on to the purchasers. In view of    the terms of the ABA and the explanation which has been submitted by the developer, there is no deficiency of service in regard to the demand of interest payable on the tax which was required to be deposited with the

ALSO READ- SUPREME COURT STAYS PUNJAB HARYANA HIGH COURT RERA JUDGMENT

  1. Electricity
  • The submission by Mr. R. Balasubramanian, learned Senior Counsel is that the initial collection of Rs. 1.50 lacs from each buyer towards BESCOM/BWSSB charges for electricity and water are admitted. Subsequently, invoking clause 23(b) of the ABA, the developer collected two lacs from each buyer towards additional  electricity  The appellants contest the entitlement of the developer to claim these  charges.
  • Clause 23(b) of the ABA is in the following terms:

“23.(b) Payments and other charges for bulk supply of electrical energy

If Company or the Maintenance Agency decides to apply for and thereafter  receives permission from BESCOM or from any other body/commission/regulator/licensing authority constituted by the Government of Karnataka for such purpose, to receive and distribute bulk supply  of  electrical  energy in the Said Project/Said Complex then the Allottee undertakes to pay on demand to the Company proportionate share as may be determined by  the  Company of all payments and charges paid/payable by the Company or the Maintenance Agency to BESCOM…The proportionate share of cost incurred by the Company for creating infrastructure like HT feeder, EHT sub stations etc. shall also  be payable by the Allottee on demand.”

According to the developer, initially an electricity connection was provided by BESCOM without insisting on the requirement of an electric sub-station. Subsequently  as occupation certificates were received for additional towers, BESCOM required a dedicated electric sub-station which was constructed by the developer at a cost of Rs. 18.01 crores. The pro rata cost for setting up this additional infrastructure was, according to the developer, payable by the allottees. When offers for possession were issued to the buyers, the following stipulation was contained in the letter:

“Our initial effort was to obtain and energize the power supply to the entire   project of 1830 apartments through individual ll KV feeders from Golahalli 66/11KV Substation. On this basis, the costing for infrastructure towards provisioning of utilities as per clause 1.14, 1.15, 23(b) and JDC of ABA was estimated at rate Rs. 127.96/sft., which was reflected in the Final Demand to D Block  customers.  However, after a detailed evaluation of the load requirement for the project as per norms, BESCOM has now stipulated that, in accordance with clause 3.2.4 of KERC Regulations, we establish a dedicated 66/11 kv Substation within our project site to cater to the needs of the project, instead of the earlier proposed scheme of 11 Kv feeders from Golahalli. The increase in cost because of this new sub-station and   allied works, over and above the originally envisaged 11KV scheme is estimated  @Rs. 18.01 Cr., thereby increasing the total infrastructure cost recovery towards provisioning of utilities to Rs. 188.00/sft. In view of the above said amounts are being recovered on the basis of provisional estimates. On commissioning and energizing the substation, the company shall arrange a certificate from independent chartered accountant/chartered engineer to arrive at the actual cost incurred. Your share of the said actual cost by the Company shall be duly intimated to you accordingly. If it is found that excess amount paid by you, over and above the    actual cost incurred by the company, said excess amount so collected shall be refunded to you without interest. If the actual expenses exceeds the estimated amount computed @Rs. 188/- sq. ft. then demand for the shortfall amount shall be raised through further demand on the owner of the property and shall be payable    by you. We would further like to bring to your kind attention that the provision of 66/11KV substation will ensure better quality uninterrupted power supply as compared with the previously planned scheme of 11KV’ reeders.”

  • R. Balasubramanian, learned Senior Counsel contends that clause 23(b) relates to receiving and distributing the bulk supply of electrical energy to “the said project/said complex” which is defined as “project under the name and style of “New Town DLF BTM Extension”. According to the submission, the charges have been collected for the entire New Town project and not for Westend Heights alone. In this context it has also been submitted that distribution of electricity is governed by the KERC Regulations 2006. While planning the project, the developer calculated the cost of the 66/11 KV sub-station and collected charges from each of the 1830 buyers.   Hence, it has been submitted that there was no requirement of additional bulk supply   of electricity for the nineteen hundred buyers. In this context, the formulation in the written submissions is extracted below:

“(under) regulation 3.02(e) of KERC (Conditions of Supply of Electricity by the Distribution Licensee) Regulations 2004, it is mandatory to set up 66 KV supply line/KV substation if the demands goes beyond 7500 KVA. Further under regulation

3.2.4 KERC (Recovery of Expenditure for Supply of Electricity) Regulations 2004:“In case of layouts/buildings requiring power supply and the requisitioned load is more than 7500 KVA, the developer/Applicant shall provide the space for erection of sub- station and also bear the entire charges of such a sub-station and associated lines/equipments. The work shall be carried out either by the Licensee duly  recovering the charges as per estimate or by the Applicant himself through appropriate class of licensed contractor by paying 10% of the estimate  as  supervision charges to the Licensee.”

  • The NCDRC has upheld the collection of the charges towards electricity based on the terms of the ABA. There is no infirmity in the finding of the NCDRC, which is based on the provisions contained in clause 23(b) of the The charges recovered are not contrary to what was specified in the contract between the parties.
  1. Parking
  • The appellants seek a refund of an amount of Rs. 2.25 lacs collected from each buyer towards car parking. The submission is that under Section 3(f) of the Karnataka Apartment Ownership Act 1972, common areas and facilities include parking areas. According to the appellants, the flat buyers had already paid for the super area in terms of clause 1.6 of ABA including common areas and facilities which would be deemed to include car parking under the KAO Act. The relevant portion of clause 1.6 is extracted below:

“1.6. The Allottee agrees that the Total price of the said Apartment is calculated on the basis of its Super Area only (as indicated in clause 1.1.) Except the parking space, additional car parking space which are based on fixed valuation….”(emphasis supplied)

  • We are unable to accede to the above submission. The ABA contained a break- up of the total price of the apartment. Parking charges for exclusive use of earmarked parking spaces were separately included in the break-up. The parking charges were revealed to the flat buyers in the brochure. The charges recovered are in terms of the agreement.
  • The decision of this Court in Nahalchand Laloochand Private Limited Panchali

Cooperative Housing Society Limited turned on the provisions of the Maharashtra Ownership Flats Act 1971, as explained in the subsequent decision of this Court in DLF Limited v. Manmohan Lowe. The demand of parking charges is in terms of the ABA  and hence it is not possible to accede to the submission that there was a deficiency of service under this head.

ALSO READ- RERA NCLT CONSUMER FORUM FOR DELAY IN POSSESSION

 In This backdrop the developer has not disputed these communications. Though these are four communications issued by the developer, the appellants submitted that they are not isolated aberrations but fit into a pattern. The developer does not state that it was willing to offer the flat purchasers possession of their flats and the right to execute conveyance of the flats while reserving their claim for compensation for delay. On the contrary, the tenor of the communications indicates that while executing the Deeds of Conveyance, the flat buyers were informed that no form of protest or reservation    would be acceptable. The flat buyers were essentially presented with an unfair choice of either retaining their right to pursue their claims (in which event they would not get possession or title in the meantime) or to forsake the claims in order to perfect their  title to the flats for which they had paid valuable consideration. In this backdrop, the simple question which we need to address is whether a flat buyer  who  seeks  to espouse a claim against the developer for delayed possession can as a consequence of doing so be compelled to defer the right to obtain a conveyance to perfect their title. It would, in our view, be manifestly unreasonable to expect that in order to pursue a   claim for compensation for delayed handing over of possession, the purchaser must indefinitely defer obtaining a conveyance of the premises purchased or, if they seek to obtain a Deed of Conveyance to forsake the right to claim compensation. This basically is a position which the NCDRC has espoused. We cannot countenance that view.

In other words, what the developer holds out as a defence is that though there has been a failure on their part to provide the amenities, the flat buyers have the benefit of facilities in the surrounding area which has become urbanised. We cannot agree with this line of submissions. The reply of the developer seeks to explain the failure to construct the facilities on the ground that the “existing population cannot sustain these facilities” – a school, commercial complex and health care facilities. This    is a case involving an experienced developer who knew the nature of  the  representation which was being held out to the flat purchasers. Developers sell dreams to home buyers. Implicit in their representations is that the facilities which will be developed by the developer will provide convenience of living and a certain lifestyle based on the existence of those amenities. Having sold the flats, the developer may   find it economically unviable to provide the amenities. The flat purchasers cannot be   left in the lurch or, as in the present case, be told that the absence of facilities which were to be provided by the developer is compensated by other amenities which are available in the area. The developer must be held accountable to its representation. A flat purchaser who invests in a flat does so on an assessment of its potential. The amenities which the builder has committed to provide impinge on the quality of life for the families of purchasers and the potential for appreciation in the value of the flat.    The representation held out by the developer cannot be dismissed as chaff. True, in a situation such as the present it may be difficult for the court to quantify the exact nature of the compensation that should be provided to the flat buyers. The general appreciation in land values results in an increase in the value of the investment made by the buyers. Difficulties in determining the measure of compensation cannot however dilute the liability to pay. A developer who has breached a clear representation which has been made to the buyers of the amenities which will be provided to them should be held accountable to the process of law. To allow the developer to escape their obligation would put a premium on false assurances and representations made to the flat purchasers. Hence, in factoring in the compensation which should be provided to the flat buyers who are concerned in the present batch of appeals, we would necessarily have to bear this issue in mind.

ALSO READ- LIMITATION IN FILING APPEAL RERA PUNJAB APPELLATE TRIBUNAL

Thus the judgment of NCDRC clearly suffers from clear perversity and patent errors of law. With this new judgment of The Supreme Court. It clearly paves the way for consumers and home buyers to take possession with protest or without protest and then file a case before RERA Authority or consumer forum to take the interest compensation for the delay.A path breaking judgment which will set a new precedent in real estate sector

For case specific Advice Please call best/top/expert consumer/RERA Advocate in Chandigarh Mohali Panchkula Zirakpur

This post is written by Advocate Satish Mishra, founder of Legal Seva Law firm where knowledge is power and ignorance is sin. To be alert and vocal about your rights when it comes to delay in delivery of possession by companies and real estate Developers