Post covers Ambika Realcon Punjab RERA Complaint where Punjab RERA Grants Interest for Delayed Possession: Fit-Out Possession Without Occupancy Certificate Held Invalid.
To file a complaint against Ambika Realcon with the Punjab Real Estate Regulatory Authority (RERA), visit the RERA Punjab Official Portal. Buyers can lodge a grievance under Section 31 of the Act to claim delayed possession interest, refunds, or compensation for projects like Florence Park or La Parisian.
In an important judgment dated 12 May 2026, the Punjab Real Estate Regulatory Authority (RERA) held that:
“Fit-out possession offered without Occupancy Certificate cannot be treated as valid possession.”
Ambika Realcon Complaint in RERA Punjab
The Authority directed the builder to pay delayed possession interest to the homebuyers under Section 18(1) of the RERA Act, 2016.
📄 Bhupesh Rana & Ambika Rana vs Ambika Realcon Pvt. Ltd.
Punjab RERA – Decision dated 12.05.2026
Common Grievances
- Delayed Possession: Builders failing to hand over apartments within agreed timelines.
- Arbitration Defense Rejection: The Authority consistently holds that arbitration clauses in buyer agreements cannot override a buyer’s right to seek RERA remedies.
- Premature Demands: Developers issuing demand letters before securing the mandatory Occupation Certificate (OC) or without factoring in delay compensation
📌 Background of the Case
The complainants booked an apartment in:
- Project: Florence Park, New Chandigarh
- Developer: Ambika Realcon Pvt. Ltd.
- Flat No.: FP/ASTER/B/502
- Tower: Aster B (Tower No. 2B)
As per the Apartment Buyer Agreement dated 18.12.2021, possession was to be delivered by:
📅 31.12.2022
The buyers had already paid approximately:
💰 ₹61.87 lakh
However, possession was not delivered within the stipulated period.
⚖️ Buyers’ Main Grievance
The complainants argued that:
- Builder demanded further payment through letter dated 05.12.2023
- Possession was offered without:
- Occupancy Certificate (OC)
- Completion Certificate (CC)
- No compensation for delay was incorporated
- Builder failed to provide a definite timeline
The buyers sought:
✔ Valid possession
✔ Delayed possession interest
✔ Quashing of illegal demand notice
🏛 Builder’s Defence
The builder argued:
- Buyers had delayed certain payments
- Arbitration clause existed in the agreement
- Covid-19 period caused delay
- Contractual clauses were binding
The builder also sought:
- Reference of dispute to arbitration
⚖️ Punjab RERA’s Key Findings
🔹 Arbitration Clause Cannot Override RERA Rights
Punjab RERA rejected the arbitration objection and held:
Statutory remedies under RERA cannot be defeated by arbitration clauses.
The Authority relied on earlier precedents and clarified that:
- Buyers are free to invoke remedies under RERA.
🔹 Covid-19 Excuse Rejected
The Authority made an important observation:
- Agreement was executed on 18.12.2021
- Covid pandemic had already occurred much earlier
Thus:
Builder cannot take benefit of Covid-19 after entering agreement post-pandemic.
🔹 One-Sided Clauses Declared Unfair
Punjab RERA referred to the Supreme Court judgment in:
- IREO Grace Realtech Pvt. Ltd. vs Abhishek Khanna
and observed:
One-sided and unreasonable clauses in builder agreements amount to unfair trade practice.
🔍 Fit-Out Possession Without OC Held Invalid
This became the most important aspect of the ruling.
The builder had earlier offered:
- “Fit-out possession” on:
- 05.12.2023
- 12.02.2025
However:
❌ Occupancy Certificate had not been obtained.
Punjab RERA held:
Such possession cannot be treated as lawful possession under RERA.
The Authority noted that:
- Occupancy Certificate was obtained only on 01.10.2025
- Valid possession was finally offered on 07.11.2025
💰 Interest Awarded by Punjab RERA
Punjab RERA held that:
- Delay period runs from:
📅 01.01.2023 to 07.11.2025
The Authority directed payment of:
✔ Interest @ 10.80% per annum
(SBI MCLR + 2%)
on the deposited amount under:
- Section 18(1) of RERA Act
📊 Interest Calculation
As recorded in the order:
- Principal amount considered:
💰 ₹61,87,773 - Total delayed possession interest awarded:
💰 ₹19,02,904
The Authority directed payment within:
📅 90 days
📌 Key Legal Takeaways
✔ Fit-out possession without OC is invalid
✔ Occupancy Certificate is mandatory for lawful possession
✔ Arbitration clauses cannot override RERA remedies
✔ Post-Covid agreements cannot use pandemic as blanket excuse
✔ Section 18 RERA gives statutory right to delayed possession interest
🧑⚖️ Why This Judgment Matters
This ruling is highly important for homebuyers facing:
- Delayed possession
- Illegal fit-out possession offers
- Demands without OC/CC
- Builder reliance on one-sided clauses
The judgment reinforces:
“Lawful possession begins only after Occupancy Certificate.”
🔍 Look out for More on my website for below-
Punjab RERA delayed possession case
Fit out possession without OC illegal
Section 18 RERA interest Punjab
Ambika Realcon Florence Park case
Occupancy Certificate RERA law
Builder delay compensation India
📣 Suggested Caption
“Punjab RERA rules that fit-out possession without Occupancy Certificate is not valid possession. Buyers entitled to delayed possession interest under Section 18 RERA.”
More on 99888-17966