RERA Appeal High Court Chandigarh Panchkula Gurugram

RERA Appeal High Court Chandigarh Panchkula Gurugram

This post covers RERA Appeal High Court Chandigarh Panchkula Gurugram wherein after RERA Appellate Tribunal Order of Panchkula Gurugram Authority is challenged. After RERA Panchkula-RERA Gurugram order, first Appeal lies to Haryana Real Estate Appellate Tribunal and of RERA Punjab Authority to Real Estate Appellate Tribunal, Punjab under Section 44 of the Real Estate (Regulation … Read more

NO RERA COMPENSATION FOR SUBSEQUENT ALLOTTEE- AO PANCHKULA

RERA SUBSEQUENT ALLOTTEE

Post covers recent ruling of RERA Panchkula’s Adjudicating Officer (AO) wherein the compensation has been denied to Subsequent Allottee but though the refund and interest already stood granted to him by RERA Authority when the complaint was filed for compensation separately. It simply says NO RERA COMPENSATION FOR SUBSEQUENT ALLOTTEE- AO PANCHKULA.  A “subsequent allottee,” … Read more

Title Search Property Report Zirakpur Derabassi Panchkula

Title Search Lawyer Zirakpur Derabassi

Buying property in Zirakpur Derabassi Panchkua, then you must know Title Search, Due Diligence RERA fact-check report about project first. Post covers extensively what all needs to be seen in the project legally and what all compliances must be followed by builder. The post is a master education piece which will minimize your risk to … Read more

Caveat Before RERA Appellate Tribunal Haryana

Caveat Before RERA Appellate Tribunal Haryana

Post covers Caveat Before RERA Appellate Tribunal Haryana against the orders of HRERA Panchkula and HRERA Gurugram whenever in Appeal. Caveat is basically a remedy in law available to both the parties in lis that whenever appeal is preferred by either of them, it is the bounden duty of court to inform the other party … Read more

ARREST SHOWCAUSE NOTICE PENALTY RERA EXECUTION

ARREST SHOWCAUSE NOTICE PENALTY IN RERA EXECUTIONS

Post covers Arrest Showcause Notice Penalty In Rera Executions. Can builder be arrested under RERA via showcause Notice or Section 63 Penalty is discussed in detailed. According to Section 63 of the Real Estate (Regulation and Development) Act, 2016, the promoter of a project is liable to pay a penalty of up to 5% of … Read more

Opera Infratech Punjab RERA Complaint Case

THIS POST COVERS PUNJAB RERA COMPLAINT AGAINST Opera infratech

THIS POST COVERS PUNJAB RERA COMPLAINT AGAINST Opera infratech The present post will cover and give an overview of the case and it will give you a brief yet precise outline regarding all the major facts and issues involved in this particular case which basically revolves around claiming, transferring and releasing of the property as … Read more

RERA CHANDIGARH AUTHORITY LAWYER ADVOCATE LEGAL ADVISOR

RERA CHANDIGARH AUTHORITY LAWYER ADVOCATE LEGAL ADVISOR

Chandigarh UT do have RERA Authority like RERA Punjab Authority and Haryana RERA Panchkula Authority but not that active since there is dearth of Real Estate Projects in Chandigarh. This can be made from the fact that the under the list of projects it shows figure zero. So certainly there is not much use of … Read more

RERA Property Advisor Chandigarh Panchkula Mohali Kharar Zirakpur

RERA Property Advisor Chandigarh Panchkula Mohali Kharar Zirakpur

Thinking of buying a property in Tricity, then talking to RERA Expert property advisor is a must. They can guide you well to understand the intricacies of a project when you are investing your hard earned money. A RERA Property Advisor helps navigate India’s Real Estate (Regulation and Development) Act (RERA) for buyers, developers, and … Read more

ATS Golf Meadows Lifestyle RERA Punjab Complaint

ATS Gold Meadows Lifestyle RERA Punjab Complaint

Post covers interest for delay in possession in ATS Golf Meadows Lifestyle RERA Punjab Complaint. To pay outstanding amount. Complaint Against ATS Estate Private Limited and Geenu Pawa This post is a summary of judgment wherein the complainant applied for one apartment in ATS Golf Meadows Lifestyle situated at village Madhopur, Tehsil Dera Bassi, District Mohali. … Read more

RERA Punjab Recovery as Arrears of Land Revenue

RERA Execution Recovery

Now that you have got order from RERA Punjab Authority but still clueless what to do next. Then this post will guide you what follows after you have won the case from Punjab Real Estate Regulatory Authority be it refund, interest or compensation. I know it is complex and time consuming but that’s a part … Read more

RERA Punjab Haryana Property Advice Lawyer

RERA Punjab Haryana Property Advice Zirakpur Kharar Derabassi

This post is a must for all those interested to buy property/flat/plot in Zirakpur Kharar Derabsssi or we can say District SAS Nagar (Mohali) in general. RERA Punjab Haryana Property Advice Zirakpur Kharar Derabassi for all residents who have questions related to the project from legal angle. RERA Punjab Haryana Property Lawyers will assist you … Read more

Mona City Homes Township RERA Punjab Case

Mona City Homes Township RERA Punjab Case

Post covers Delay in Possession of a Flat in Mona City Homes Township case before RERA Punjab Authority wherein Refund granted along with interest for deficiency in services. Complaints against Mona City Homes Township primarily involve delay in possession, construction halts, project discontinuation, and issues with amenities/quality, leading many allottees to file cases with RERA Punjab seeking interest for delay, refunds, or compensation for deficiencies, … Read more

RERA Case After Delivery of Possession Before Authority

RERA Case After Delivery of Possession Before Authority

Post covers RERA Case After Delivery of Possession wherein complainant alleges builder has done acts in violation of Section 14. Also case pending before High Court Chandigarh. The case was dismissed since the complainant failed to led evidence that showed deficiencies on part of builder. The complaint was filed before the regulatory authority by the … Read more

RERA Complaint Tristar Infrastructures for Refund

RERA Complaint Tristar Infrastructures for Refund

RERA Punjab Tribunal awarded compensation in non-rera registered property for delay in possession against Tristar Infrastructures plus refund. Judgement Digest: Gurdeep Singh v. Tristar Infrastructures Case Briefing: Complainant Gurdeep Singh booked 2BHK floor and vide flat buyer agreement dated 09.02.2013 Unit no. 33GF. The unit was allotted to complainant in the project Tunis Premium Homes … Read more

PARADIGM BUSINESS VENTURES Consumer Complaint

PARADIGM BUSINESS VENTURES Consumer Complaint

Post covers PARADIGM BUSINESS VENTURES Consumer Complaint Of project Hermitage park possession delayed. SUNNY DHURIA V. M.S PARADIGM BUSINESS VENTURES This is a suit filed before the State Consumer Disputes Redressal Commission, Punjab, Chandigarh where the complainant filed a complaint against the respondents under Section 17 of the Consumer Protection Act, 1986, seeking compensation. COMPLAINANT: … Read more

CHANDIGARH OVERSEAS PVT LTD RERA Complaint

CHANDIGARH OVERSEAS PVT LTD RERA Complaint

CHANDIGARH OVERSEAS PVT LTD RERA Complaint wherein refund of payment allowed with interest SBI MCLR +2%.

JUDGEMENT SUMMARY of Complaint before RERA Punjab Authority against CHANDIGARH OVERSEAS PVT LTD RERA Complaint

HARISH MINOCHA V. CHANDIGARH OVERSEAS PVT. LTD., 7th July, 2020

Today we are going to talk about the case of Harish Minocha v. Chandigarh overseas Pvt. Ltd., 7th July, 2020. The advocate for the complainant side was Ms. Banni Chibbar and for the respondent side was ex- parte.

Read more

Future City Developers Punjab RERA Complaint

Future City Developers Punjab RERA Complaint

Future City Developers Punjab RERA Complaint wherein mutual settlement was arrived with complainants for removing deficiencies. JUDGEMENT SUMMARY SAURABH KHANNA V. M/S FUTURE CITY DEVELOPERS PVT. LTD, 26th June, 2020 Today we are going to talk about the case of Saurabh Khanna v. Future City Developers Pvt . ltd, 26th June, 2020. The advocates for … Read more

RERA Punjab Complaint Primary Estates & Developers Pvt Ltd

RERA Punjab Complaint Primary Estates & Developers Pvt Ltd

Complaints against Primary Estates & Developers can be filed with the Punjab RERA Authority (via Form M) due to project delays and failure to refund amounts for projects like Arcadia Green Homes in Mohali, with legal precedence for interest compensation under Section 18. Note that the company is reported to be permanently closed.  The post … Read more

CONSUMER COMPLAINT AGAINST BARNALA BUILDERS & PROPERTY CONSULTANTS

CONSUMER COMPLAINT AGAINST BARNALA BUILDERS & PROPERTY CONSULTANTS

Complaints against Barnala Builders & Property Consultants (specifically regarding projects like Maya Garden) often involve allegations of delayed possession, failure to obtain Completion/Occupancy Certificates, and poor construction quality, leading to RERA Punjab and consumer forum cases. Courts have ordered refunds, compensation for delays, and interest payments to affected allottees. In this post we will discuss about … Read more

Consumer RERA Complaint Maya Garden City (Barnala Builders)

Consumer RERA Complaint Maya Garden City (Barnala Builders)

Complaints against Maya Garden City (Barnala Builders) in Zirakpur often involve delays in possession, lack of completion certificates, and unfulfilled promised returns. RERA Punjab has directed the builder in several cases to pay interest for delayed possession, compensate for mental agony, or refund amounts, with some complaints highlighting issues in both residential and commercial units.  … Read more

Tulip Infratech Pvt. Ltd Haryana RERA Complaint Case

Tulip Infratech Pvt. Ltd Haryana RERA Complaint Case

Complaints against Tulip Infratech in Haryana RERA often relate to project delays, failure to deliver possession, and non-compliance with quarterly progress report submissions. Numerous cases, including suo-motu actions (e.g., Complaint No. 1998 of 2022, 5232-2019), have been registered by HRERA Panchkula/Gurugram regarding violations of Section 11 of the RERA Act, 2016. In this post we will … Read more

Dream Century Housing Consumer Complaint RERA Punjab

Dream Century Housing Consumer Complaint RERA Punjab

In this post we will discuss about Consumer Complaint against Dream Century Housing wherein consumer purchased a unit and the opposite party failed to deliver possession of the unit within the Stipulated Period. Then homebuyer is likely to apply for completion certificate within 6 months and thereafter shall be offering possession of the said unit. … Read more

RKM Housing Ltd Consumer Complaint RERA Punjab

RKM Housing Ltd Consumer Complaint RERA Punjab

Complaints against RKM Housing Ltd, particularly regarding projects like RKM City in Mohali, often involve delays in handing over possession, lack of necessary approvals (CLU), and failure to refund booking amounts. Affected buyers have successfully approached RERA Punjab and Consumer Courts for refunds with interest.  In this post we will discuss about Punjab RERA complaint against RKM … Read more

Consumer RERA Complaint against Emaar Mgf Land Limited

Consumer RERA Complaint against Emaar Mgf Land Limited

Complaints against Emaar MGF Land often involve delayed possession, seeking compensation (interest/damages), and issues with service deficiency, commonly addressed through consumer forums (NCDRC) and RERA, with landmark Supreme Court rulings (like Emaar v. Aftab Singh) affirming consumer court jurisdiction despite arbitration clauses. While some cases settle amicably, others proceed, with authorities often ordering interest (e.g., 9-12%) … Read more

Gillco Developers and Builders Pvt Ltd Consumer RERA Case

Gillco Developers and Builders Pvt Ltd Consumer RERA Case

Gillco Developers and Builders Pvt Ltd has faced multiple RERA Punjab cases regarding project delays and refund requests, with several matters settled through mutual compromises. Key cases involve Gillco Park Hills and other projects, with rulings focusing on refund of booking amounts, interest on delayed possession, and compliance with project completion dates. In this post … Read more

Manohar Infrastructure & Constructions RERA Punjab Complaint

Manohar Infrastructure & Constructions RERA Punjab Complaint

Manohar Infrastructure & Constructions Pvt. Ltd. faces multiple consumer complaints, primarily regarding projects like “Palm Springs” and “Palm Garden” in Mullanpur/New Chandigarh. Grievances involve failure to deliver possession within promised timelines (often 2 years), lack of requisite project approvals, and non-compliance with regulations. In this post we will discuss about RERA complaint against Manohar Infrastructure … Read more

Refund of Pre Deposit amount for RERA Appeal Haryana

Refund of Pre Deposit amount for RERA Appeal Haryana

In this post we will discuss about the detailed procedure for getting back the mandatory deposit amount required for filing an appeal in HREAT. How to get refund of the amount deposited by the Appellant with the Haryana Real Estate Appellate Tribunal Once the impugned order is held to be without jurisdiction and appeal filed … Read more

RERA Punjab Complaint against Land Twister Homes Kharar

RERA Punjab Complaint against Land Twister Homes Kharar

Complaints against Land Twister Homes (Kharar-Landran Road, Sector 116, Mohali) in RERA Punjab often involve significant delays in possession, with allegations of no construction progress despite payments made. Buyers can file complaints (Form M/N) via the Real Estate Regulatory Authority, Punjab website for relief.  Key Aspects of Complaints against Land Twister Homes: Project Issues: Complaints allege non-delivery of … Read more

Agreement to Sell RERA Punjab Haryana Panchkula

Agreement to Sell RERA Punjab Haryana Panchkula

An Agreement to Sell (ATS) in RERA Punjab/Haryana/Panchkula is a mandatory contract ensuring transparency for property deals, detailing project plans, payment schedules, and developer obligations (like timely possession) as per the Real Estate (Regulation and Development) Act, 2016. It binds the promoter to approved layouts and specifies buyer/seller rights, with RERA enforcing adherence to these … Read more

Limitation in Filing Appeal RERA Punjab Appellate Tribunal

Limitation in Filing Appeal RERA Punjab Appellate Tribunal

For appeals to the RERA Punjab Appellate Tribunal, the primary limitation is 60 days from receiving the Authority’s order, but the Tribunal can condone delays if “sufficient cause” is shown, often requiring a formal condonation of delay application with the appeal. Appeals must follow specific forms (Form ‘L’ for Punjab), include required documents, fees (e.g., Rs. 1000 DD), and … Read more

Pre Deposit Before RERA Appeal Punjab Haryana Authority

Pre Deposit Before RERA Appeal Punjab Haryana Authority

Under Section 43(5) of the RERA Act, 2016, a promoter must deposit at least 30% of the penalty or the total amount ordered (including interest/compensation) before the Real Estate Appellate Tribunal can hear an appeal. This mandatory pre-deposit ensures buyer protection and verifies the promoter’s bona fides.  This report looks into a judgment of Punjab … Read more

Punjab RERA Complaint against Sushma Buildtech Ltd Homework

Punjab RERA Complaint against Sushma Buildtech Ltd Homework

Complaints against Sushma Buildtech Limited, primarily regarding project delays (e.g., Sushma Crescent, Infinium) and demands for interest or refunds, are commonly filed with the Real Estate Regulatory Authority (RERA) Punjab. RERA Punjab has handled numerous cases, with some resulting in directives for interest payments for delayed possession (e.g., 9.3% rate) or dismissals due to settlements or … Read more

Sandwoods Infratech Projects RERA Punjab Complaint

Sandwoods Infratech Projects RERA Complaint

Complaints against Sandwoods Infratech Projects (specifically in Punjab/Himachal) involve issues with project delays, demands for booking amount refunds, and interest payments for delayed possession, often linked to insolvency proceedings (CIRP) under IBC 2016. RERA authorities have directed the developer to pay interest (SBI MCLR + 2%) for delayed possession.  This is a post of Sandwoods … Read more

RERA Punjab Complaint against ATS Estate Private Ltd

RERA Punjab Complaint against ATS Estate Private Ltd

This post covers RERA Punjab Complaint against ATS Estate Private Ltd before Adjudicating Officer wherein the refund of entire amount was allowed along with interest & further compensation for delay in possession on account of mental agony, pain and harassment. RERA Punjab Authorities are strict for builder for defying possessions timeline where customer suffers for … Read more

Haryana RERA Panchkula Complaint against Piyush Buildwell

Haryana RERA Panchkula Complaint against Piyush Buildwell

This post is a judgment digest of Haryana RERA Panchkula Complaint against Piyush Buildwell wherein the builder demanded higher amount for conveyance deed which was not as per agreed terms of builder buyer agreement. Hence court directed to take reasonable amount for getting conveyance deed done. Also Read- Execution of Rera Panchkula Orders In combine … Read more

RERA Punjab Complaint against Country Colonizers Private Limited

RERA Punjab Complaint against Country Colonizers Private Limited

Post Covers RERA Punjab Complaint against Country Colonizers Private Limited for delay in possession and getting monthly interest from the builder till valid legal offer of possession is made. In this post, we bring you a judgment digest of a case of Punjab RERA Complaint against Country Colonizers Private Limited for delay in possession and … Read more

Adjudicating Officer RERA Panchkula RERA Punjab

Adjudicating Officer RERA Panchkula RERA Punjab

Post covers powers of Adjudicating Officer RERA (AO) at Panchkula Haryana RERA Authority and  Punjab RERA. Sole claims of compensation entertained after Newtech judgment and refund-interest prayer not to be nixed. Due to the rapid growth of the Indian economy and the continuous migration of people from rural to urban areas, the need of housing … Read more

Case of forfeiture of amount by Builder RERA Panchkula

Case of forfeiture of amount by Builder RERA Panchkula

Post is about forfeiture by builder of earnest amount while buying a unit in any project and what is the RERA rule regarding it. Let’s read. There are many instances where Builders unilaterally cancel the allotment of unit and forfeit the money of home buyer. The said practise of Builders has been done to cover … Read more

Quick Facts Haryana RERA Panchkula & Punjab RERA Authority

Quick Facts Haryana RERA Panchkula & Punjab RERA Authority

Post covers quick facts RERA about Haryana Panchkula Authority and Punjab Authority at Chandigarh. Here in this post, we will cover quick facts about Haryana RERA Panchkula Authority and Punjab RERA Authority at Chandigarh. Both these authorities are working stead fast to solve the problems of homebuyers in the region be it delay in possession, … Read more

PUDA APPEAL DISMISSED BY RERA APPELLATE TRIBUNAL PUNJAB

PUDA APPEAL DISMISSED BY RERA APPELLATE TRIBUNAL PUNJAB

Yes, the Punjab Urban Planning and Development Authority (PUDA) has had multiple appeals dismissed by the RERA Appellate Tribunal (REAT) in Punjab, often for failing to provide valid reasons for delays in project possession, not proving completion, or for procedural failures, leading to homebuyers getting refunds with interest. The tribunal consistently rules against PUDA when … Read more